What Is RC Building Retrofitting Calculation?

The seismic safety of a building retrofitted per TBDY 2018 is determined with the assessment principles given for existing buildings. In other words, retrofitting calculation is not a separate calculation; it is the repetition of the same performance analysis with the retrofitted members.

The code defines retrofitting at member and system level: wrapping columns with fiber-reinforced polymer, RC or steel, enlarging the column section (jacketing), wrapping beams, new RC shear walls and retrofitting infill walls. Each method affects stiffness, strength and ductility differently; for example, wrapping methods do not increase the flexural capacity of the column, whereas jacketing does.

In StatiCAD, retrofitting is defined as a member property. With the “Include retrofitting in calculation” option off, the program calculates the existing state of the building, and with it on, the retrofitted state; stiffness, capacity, damage limits, building verdict and report are updated together.

What Does StatiCAD Do in RC Retrofitting?

Including member and system retrofitting in the calculation and reporting it, as corresponding to the code.

Column Retrofitting

  • Fiber-reinforced polymer (FRP) wrapping, Annex 15B: confined concrete model, damage limits and shear contribution
  • Check of lap-splice length deficiency with FRP (Annex 15B.4) and required FRP thickness
  • Section enlargement (jacketing): 1–4 faces, jacket longitudinal reinforcement and stirrups; 0.9 factor on stiffness and strength
  • Shear strength increase with RC jacketing and steel jacketing

Beam Retrofitting

  • FRP wrapping: confined model and shear contribution, subject to the strip spacing condition
  • Contribution to shear strength with external stirrups
  • As required by the code, the rule that wrapping methods do not increase beam flexural capacity is applied in the calculation

Shear Wall and System Retrofitting

  • Wrapping of shear wall end regions with FRP
  • New RC retrofit shear wall: ignored in the model before retrofitting, evaluated as a new member afterwards
  • Check of diameter, spacing, depth and shear capacity of the anchors between the shear wall and the existing frame
  • Reminder notes for the shear wall end region and foundation

Infill Wall Retrofitting (Annex 15C)

  • Retrofitting with steel-mesh reinforced plaster and FRP diagonal strip
  • Modeling with an equivalent diagonal compression strut (plus a tension strut for FRP)
  • Damage region by shear capacity and drift angle limits (TBDY Table 15.2)
  • The retrofitted infill wall takes part in the building verdict as a vertical member

Before and After in the Same Project

  • Retrofitting data is saved with the project; with the option off, the results are the same as those of the existing building
  • With the option on, stiffness, capacity, damage limits and building verdict are calculated for the retrofitted state
  • Before → after summary on the first page of the report: building performance level, 15.8 criteria percentages, retrofitted members and members whose damage region changed

Code Checks

  • Instant summary of code quantities in the property window (confinement pressure, confined strength, shear contributions)
  • Inputs that do not meet the conditions (FRP corner radius, aspect ratio, wrapping and jacket thickness, anchorage, plaster thickness, opening ratio) appear as errors or warnings in the Project Checklist
  • The stiffness and section effect of retrofitting is also reflected in the nonlinear pushover analysis

How Does It Work?

  1. Perform the performance analysis of the existing building; this is the before-retrofitting state.
  2. Enter the method and parameters in the Retrofitting tab of the property window of the columns, beams, shear walls and infill walls to be retrofitted. With multiple selection you can apply it to several members at once.
  3. Turn on the “Include retrofitting in calculation” option in Project General Settings and rerun the analysis.
  4. With the “Add before/after retrofitting comparison to report” option, put the comparison of the two states on the first page of the report.

Reports

Retrofitting information is embedded in the performance report:

  • “Retrofitting” column with method and parameters in column and beam tables
  • Anchorage ratio and end region note in the new shear wall row
  • Drift angle, capacity and damage region for retrofitted infill walls
  • Comparison of building performance level before and after retrofitting
  • Code condition rows in the Project Checklist

Verification

The relations of the retrofitting module, namely the Annex 15B confinement model, shear contributions, lap-splice check, jacket section properties and Annex 15C diagonal struts, have been compared numerically with independent calculations and hand calculations.

That, with the retrofitting option off, the results remain exactly identical to those of a building with no retrofitting defined is checked in every edition.

Details of the verification studies (Knowledge Base)

Codes and Standards

TBDY 2018 15.9–15.10 Annex 15B (fiber-reinforced polymer) Annex 15C (infill wall) TBDY 2018 Chapter 15 TS 500
Which edition? The RC retrofitting module, together with RC performance analysis, is included in StatiCAD Ultimate, Profesyonel and Betonarme editions.

Frequently Asked Questions

Which retrofitting methods can be calculated?

In columns, fiber-reinforced polymer wrapping, jacketing (section enlargement), RC jacketing and steel jacketing; in beams, fiber-reinforced polymer wrapping and external stirrups; in shear walls, fiber-reinforced polymer wrapping of the end region and new RC shear walls; in infill walls, steel-mesh reinforced plaster and fiber-reinforced polymer diagonal strips.

Do I need two separate projects for before and after retrofitting?

No. Retrofitting is stored in the same project as a member property. With the “Include retrofitting in calculation” option off, the existing building is calculated, and with it on, the retrofitted building; the comparison of the two states can be put on the first page of the report.

What is the difference between jacketing and fiber-reinforced polymer wrapping?

Per TBDY 2018, wrapping methods (fiber-reinforced polymer, RC and steel jacketing) do not increase the flexural capacity of the column; they increase ductility and shear strength. Jacketing, since it enlarges the section, increases stiffness, flexural and shear strength together. StatiCAD accounts for each method with these differences.

Is retrofitting also considered in pushover analysis?

Yes. The stiffness and section effects of fiber-reinforced polymer, jacketing, new shear wall and infill wall retrofitting are also reflected in the nonlinear pushover analysis. Additional shear checks such as steel jacketing, external stirrups and anchorage are reported in the linear assessment.

What happens if I enter a retrofitting that does not meet the code condition?

The calculation does not stop; the relevant condition appears as an error or warning row in the Project Checklist and is also shown in the summary in the property window. The final decision is made by the engineer.

Is there retrofitting calculation for masonry buildings?

Yes. In masonry buildings, retrofitting can be done with shotcrete, tie columns, fiber-reinforced polymer and new walls. See the Masonry Building Software page for details.

Related Pages

Complete your retrofitting project in the same model

Download the demo version and try before and after retrofitting assessment on your own project for free.